Further sections of the development complete

Block 5: Internally, air testing continues; Nassau St façade, windows completing, with fit-out progressing across the block.

Block 6 & 7: Scaffold being progressively struck & Cladding almost complete.

Block 8: Balcony Glazing and Cladding being completed, façade snagging and fit out progressing.

1 Fitzroy Place: Windows complete with façade snagging and M&E commissioning.

2 Fitzroy Place: Completing windows at Level 8 Ground and ground floor working towards final handover, landscaping completing outside restaurant.


Safety gantry removed from Office Blocks 1 & 2 Mortimer Street

1 Fitzroy Place: Windows complete with façade snagging and M&E commissioning. 2 Fitzroy Place: Completing windows at Level 8 Ground and ground floor working towards final handover, landscaping completing outside restaurant. External works preparation on Cleveland St and Mortimer St; statutory service connections to Mortimer St with retail façade works closing up.


New building starts to be revealed as first area of scaffold protection is removed on Nassau St.

Block 6 & 7 : Scaffold being progressively struck & Cladding completed. Block 8 : Balcony Glazing and Cladding being completed. Block 5 : Façade repairs and Window installation. External works preparation on Cleveland St and Mortimer St.


Safety gantry removed from Office Block 1

Office Block 1: Windows complete to Level 5 and curtain walling to 6-8 nearing completion. Roof works and plant installation continues across all other blocks. The safety gantry has been removed to the front of Office Block 1.


Mortimer St gantry being removed

All tower cranes have now been removed from site and the continuous suspension of the disabled parking bays in Nassau St has now finished. Windows to both Office Blocks are nearing completion.

The cladding and glazing is complete on residential Block 8. Works to the façade and windows continue on Block 5 with the Mansard structure being almost complete.